Construction progress in our absence: painters finished with all of the walls and the interior doors have been primed; wood supports have been installed on all of the perimeter walls in preparation for the fixture installation; glass has been installed in the patio door; and the concrete floor preparation started.
We ran into a big snag on Friday with the light fixtures that took us for ever to choose. It seems one of the component suppliers for Cooper Lighting is unable to deliver a needed part to manufacture our lights, so they anticipate a delay into mid-March. Well, that doesn't work for us, so now we are back to the drawing board looking for a replacement fixture or some other solution. More on that on Monday.