During the weekly contractors' meeting today, our general contractor ensured us that the HVAC Habitrail installation is moving at a good pace. Just seems slow to us novices. Yesterday the demo crew removed a ramp, today they are building stairs. Also the area for the new ramp to the outside Patio Living department is prepped and should be built today or tomorrow. No drywall work today - they have to wait for the Screw Inspection before they can tape. Screw Inspection? Are you kidding me?
We received an updated construction project schedule today and pending the lights that we took forever to decide on arriving on a timely basis, we are only 1 day behind schedule. January 30 is the current projected completion date for construction. Fortunately we have 2 weeks of overrun time as the store fixtures won't deliver until February 16.